Development of Integrated Production Scheduling System in the Process Industry
2005
This study introduces a three-level hierarchical production planning and scheduling
approach developed and implemented in a resin factory. Our approach proposes at the first level a
mixed-integer linear programming for solving the aggregate planning model. At the second level, a
weighted-integer goal-programming model is developed to disaggregate the developed aggregate
plans. A sequencing algorithm is developed for the third level that tends to minimize the total weighted
tardiness. Real industrial data is used to test and validate the proposed models.