International Engineering Construction Claims and Design Variation Optimization

2013 
Based on the successful cases-two claims for the contract clauses of the measurement of work executed and two design variations optimization actually occurred in the Nigerian Railway Modernization Project,this paper summarizes the process and accomplishments of contract claims and design variations,analyzes the different treatments adopted for both lump-sum contract and unit price contract;states the negotiation skills for the project's employer or the consultant regarding to the contract claims and design variations.At last,the important conditions of the success for the claims and variations are put forward-basing on the contract tight to occupy the commanding point of the theory,following the strategy of mutual benefit and win-win results to create better benefit for the project.