Beam commissioning of the SPS LSS6 extraction and TT60 for LHC

2007 
The new fast extraction system in LSS6 of the SPS and the first 100 m of transfer line TT60 was commissioned with low intensity beam in late 2006. The layout and functionality of the main elements are briefly explained, including the various hardware subsystems and the control system. The systems safety procedures, test objectives and measurements performed during the beam commissioning are described.