Reduced-scope seimic analysis accomplished using probabilistic risk assessment techniques

1990 
In compliance with Department of Energy (DOE) Order 6430.1A, a seismic analysis was performed on DOE's Process Experimental Pilot Plant (PREPP), a facility for processing low-level and transuranic (TRU) waste. Because no hazard curves were available for the Idaho National Engineering Laboratory (INEL), DOE guidelines were used to estimate the frequency for the specified design-basis earthquake (DBE). A dynamic structural analysis of the building was performed, using the DBE parameters, followed by a probabilistic risk assessment (PRA). For the PRA, a functional organization of the facility equipment was effected so that top events for a representative event tree model could be determined. Building response spectra (calculated from the structural analysis), in conjunction with generic fragility data, were used to generate fragility curves for the PREPP equipment. Using these curves, failure probabilities for each top event were calculated. These probabilities were integrated into the event tree model, and accident sequences and respective probabilities were calculated through quantification. By combining the sequences failure probabilities with a transport analysis of the estimated airborne source term from a DBE, onsite and offsite consequences were calculated. The results of the comprehensive analysis substantiated the ability of the PREPP facility to withstand a DBE with negligiblemore » consequence (i.e., estimated release was within personnel and environmental dose guidelines). 3 refs., 1 fig.« less
    • Correction
    • Source
    • Cite
    • Save
    • Machine Reading By IdeaReader
    0
    References
    0
    Citations
    NaN
    KQI
    []