Optimization of joint grouting construction technology for Laxiwa hydropower project
2010
By optimizing the technology of laying dam insulation and cooling pipes,the joint grouting of the main dam was conducted all the year round for Laxiwa hydropower project.The application of optimized technology simplifies construction procedures,reduces the interruption in concrete placement and speeds up the construction schedule,which provides reference for similar projects.