Simulation of System Commissioning Test for UHVDC Converter Station

2017 
In order to make the commissioning of the UHVDC converter station successful and secure, the PSASP power system software tool was applied to simulate the switching test of unloaded lines, the 66kV reactors, the 66kV capacitors and the 500kV reactive power compensation equipments. All of the simulations were performed smoothly and the results are promising. Thus, they can be used to select the test limit, providing the basis for calculation, which provides reliable technical basis for the future analysis and control of UHVDC converter station system commissioning test in the future.