Evaluation of LANL Capabilities for Fabrication of TREAT Conversion Fuel

2014 
This report estimates costs and schedule associated with scale up and fabrication of a low-enriched uranium (LEU) core for the Transient Reactor Test Facility (TREAT) reactor. This study considers facilities available at Los Alamos National Laboratory, facility upgrades, equipment, installation and staffing costs. Not included are costs associated with raw materials and off-site shipping. These estimates are considered a rough of magnitude. At this time, no specifications for the LEU core have been made and the final schedule needed by the national program. The estimate range (+/-100%) reflects this large uncertainty and is subject to change as the project scope becomes more defined.