The SARAF-LINAC Project 2019 Status

2019 
SNRC and CEA collaborate to the upgrade of the SARAF accelerator to 5 mA CW 40 MeV deuteron and proton beams (Phase 2). CEA is in charge of the design, construction and commissioning of the MEBT line and the superconducting linac (SARAF-LINAC Project). The prototypes of the 176 MHz NC rebuncher, SC cavities, RF coupler and SC solenoid-Package have been tested recently. Meanwhile, the cryomodules technical specifications have been written and called for tender. This paper presents the status of the SARAF-LINAC Project at April 2019.