An Analysis on Work Delay Factors in Apartment House Construction

2007 
Work delay is one of the facts that make the reliability of construction projects decrease. Therefore, it is important to classify and prioritize the delay factors. This research analyzed key delay factors in apartment house construction through survey. The results of analysis are as follows. (1) Insufficient work force is the key delay factor in structural and finish work. (2) Improper craft of worker is the key delay factor in electrical work. (3) Incompletion of proceeding work is the key delay factor in mechanical work.