Impact of blast fragmentation on hydraulic excavator dig time

2003 
Blast fragmentation size distribution and thus blast design have been found to have a direct impact on the load and haul cycle through excavator dig time and bucket payload. Previous studies have demonstrated that by reducing the excavator dig time and increasing bucket payload, significant improvements can be made in both productivity and unit cost. Simulation work reported in the literature indicates that a 20 per cent improvement in dig time may result in only a three per cent improvement in load and haul productivity and unit cost. At the same time, a ten per cent improvement in bucket payload will directly translate to a ten per cent improvement in load and haul productivity and unit cost. Based upon these findings, extensive laboratory and field work have been undertaken in the past to correlate blast fragmentation distribution to bucket payload. In contrast, the literature reports limited studies quantifying the impact of blast fragmentation on excavator dig time. Field work was conducted at Placer Dome Asia Pacific’s Granny Smith Mine (Wallaby Pit) in Western Australia, concentrating on quantifying the impact of blast fragmentation on the dig time of a Liebherr 994 hydraulic excavator (shovel attachment with 14 m3 bucket). Fragmentation was assessed for each truck load of material using the Split Desktop system, while the excavator cycle analysis was conducted manually. Measured fragmentation P80 (fragment size at which 80 per cent of material passes) values ranged from 200 mm to 1200 mm. The field study investigated the impact of various fragmentation parameters (P20, P50, P80, cumulative per cent passing 250 mm size fraction, and uniformity index) on the average and total dig times. The results indicate that the fragmentation P80 provides the best correlation to average dig time (total dig time divided by the number of bucket passes to load a truck). The total dig time was found to be dependant upon the fragmentation P80 and the number of bucket passes to fill a truck. Monte Carlo simulation results, based upon these relationships, indicate a 26 per cent improvement in average dig time and a 12 per cent to 46 per cent improvement in total dig time (bucket passes ranging from 4 to 8), with a change in fragmentation P80 from 600 mm to 200 mm.
    • Correction
    • Source
    • Cite
    • Save
    • Machine Reading By IdeaReader
    1
    References
    15
    Citations
    NaN
    KQI
    []