SPIRAL 2 Commissioning Status and Future Prospects
2016
The first phase of the SPIRAL 2 project dealing with the high-power superconducting
linac and the two experimental areas called Neutron for Science (NfS) and Super
Separator Spectrometer (S3) is well advanced. The project is now in a phase during
which the linac components are successively installed and commissioned (the first
beam was produced in December 2014). After having briefly recalled the project scope
and parameters, the way the accelerator installation and commissioning are done is
explained. The next steps which are the DESIR low-energy experimental area and the
q/A = 1/7 heavy ion second injector are also presented.