COMMISSIONING AND OPERATION OF THE CEBAF 100 MV CRYOMODULES

2012 
The Continuous Electron Beam Accelerator Facility (CEBAF) energy upgrade from 6 GeV to 12 GeV includes the installation of ten new 100 MV cryomodules and RF systems. The superconducting RF cavities are designed to operate CW at a maximum accelerating gradient of 19.3 MV/m. To support the higher gradients and higher Q{sub L} ({approx} 3 x 10{sup 7}), a new RF system has been developed and is being installed to power and control the cavities. The RF system employs digital control and 13 kW klystrons. Recently, two of these cryomodules and associated RF hardware and software have been installed and commissioned in the CEBAF accelerator. Electrons at linac currents up to 540 {micro}A have been successfully accelerated and used for nuclear physics experiments. This paper reports on the commissioning and operation of the RF system and cryomodules.