Spent Nuclear Fuel project estimate of volatile fission products release from multi-canister overpacks

1996 
Spent N-Reactor fuel will be moved from wet pool storage to dry storage at Hanford Washington. This fuel will be sequentially loaded into a Multiple Container Overpack (MCO), moved to the cold vacuum drying station, drained, cold vacuum dried, shipped to the Canister Storage Building (CSB), staged for up to 2 years,hot vacuum dried at 300 degrees C, hot conditioned at 150 degrees C, and finally, sealed and stored for up to 75 years in the CSB.During each proposed process step, the volatile radioactive fission products released to the atmosphere were estimated.Tritium is the only volatile fission product released insignificant amounts during each process step. For an accident scenario involving interior MCO temperature of 600 degrees C for up to 8 hours, it was estimated that many volatile fission products are released.