Analysis of the failure of a large hangingwall wedge : Kidd Mining Division, Falconbridge, Ltd.

2000 
The Kidd operation mines roughly 10 000 tpd of copper and zinc ore from underground and employs about 700 personnel. In the late summer and fall of 1997, major movements in the proximity of the east wall of the Kidd open pit had been observed. The Kidd pit had been mined from 1965 to 1977 to depths of 260 m (850 ft), followed by subsequent mining by underground methods to current depths in excess of 1830 m (6800 ft). The No. 1 Mine (2600 Level to pit bottom) is approximately 90% extracted, with most of the remaining reserve between 2000 and 2500 levels. Although initial concerns centred on the stability of the pit walls, the potential ramifications of the movements to the underground were recognized and measures were implemented to ensure the safety of personnel as well as to minimize the potential damage to existing operations. In late October, damage to underground operations was observed as deep as the 2000 Level. In the final assessment, the global mobilized mass was a wedge -shaped hangingwall block extending from surface to about 610 m (2000 ft) below surface. The wedge boundaries are defined by a fault and shear zone which have continuous lengths in excess of 1070 m (3500 ft); its base by shearing through the host rock mass; and its eastern face by deep tension cracks (Fig. 1). Mined and filled excavations at the western face of the wedge allowed mobilization of a mass in excess of 30 M tonnes. Movements in excess of 75 cm (30 in.) per day were recorded on the surface stations that preceded the complete shutdown of operations on October 29, 1997. The evaluations in the days following the shut-down were centred on mitigation of immediate and future possible negative impacts on infrastructure and mining of the remaining No. 1 Mine reserves while ensuring the safety of the operators. This effort required the rapid assessment of the potential damage of the block movement on underground infrastructure, stope access, drainage and ventilation, as well as airblast potential due to the falling of a large block into the pit near the ventilation intake at the base of the pit. These assessments were presented in a previous paper (Seldon et al., 1999). In total, the lateral movement of the block on the ground surface was over 4,3 m (14 ft). This paper describes the detailed studies performed to understand the failure mechanism and to assess the impacts on future mining in No. 1 Mine.
    • Correction
    • Cite
    • Save
    • Machine Reading By IdeaReader
    0
    References
    4
    Citations
    NaN
    KQI
    []