Intermediate scale borehole (Room C): In situ data report (January 1989--June 1993)

1994 
Data are presented from the intermediate scale borehole test, an in situ test fielded in the pillar separating Rooms C1 and C2 at the Waste Isolation Pilot Plant (WIPP). The test was to provide data on the influence of scale, if any, on the structural behavior of underground openings in salt. These data include selected fielding information, test configuration, instrumentation activities, and comprehensive results from a large number of gages. Construction of the test began in December 1989, with the drilling of the intermediate scale borehole in December 1990. Gage data in this report cover the period from January 1989 through June 1993.