Production process validation of 2-[18F]-fluoro-2-deoxy-D-glucose

2003 
The aim of production process validation of 2-[18F]-fluoro-2-deoxi-D-glucose (FDG) was to check: A) equipments and services implicated in the production process were correctly installed, well documented, and worked properly, and B) production of FDG was done in a repetitive way according to predefined parameters. The main document was the Validation Master Plan, and steps were: installation qualification, operational qualification, performance qualification and validation final report. After finalization of all tests established in qualification steps without deviations, we concluded that the production process was validated because consistently produced FDG meeting its pre-determined specifications and quality characteristics