Progress in Development of the 170 GHz, 2MW Coaxial Cavity Gyrotron for ITER

2006 
The delivery of a first industrial prototype of a 170 GHz coaxial cavity gyrotron is expected in September 2006. RF tests with the gyrotron are foreseen to start in January 2007 when the superconducting (SC) magnet has been delivered. Experimental studies have been performed with a 170 GHz pre-prototype of the coaxial gyrotron in order to prove the design of main gyrotron components.
    • Correction
    • Source
    • Cite
    • Save
    • Machine Reading By IdeaReader
    1
    References
    2
    Citations
    NaN
    KQI
    []