Corrective Measures For Power Supply At 66 KV Sub Station,WTC Completion Report

1987 
This Is A Completion Report Of The Project Of Introducing Corrective Measures For Ensuring Satisfactory Power Supply At The W .T .C, Belur . Discusses The Various Stages Of The Work Viz, Supply, Erection And Commissioning Of A 10 Mva 66/11 Kv Transformer With 'On Load' Tap Changer (Oltc) With A .V .R, A Remote Tap Changing Control Panel (Rtcc) And A 1000 Kvar 11 Kv Capacitor Bank .