Analysis Of The Implementation Of Building Information Modeling For Time Control And The Implamation Methode Of Water Way Tunnel Construction In Way APU DAM, Buru District
2020
The waterway tunnel construction work for the way apu dam is an underground work that includes several complex works, with the possibility
that the fulfillment of the construction schedule may be delayed. On the other hand, there is information technology using Building Information Modeling
(BIM) which can help smooth development. Researchers are interested in examining how the three building image modeling that has been given
complete information can affect the implementation method and time control. The researcher formed a model 3 building image and filled it with detailed
construction information, then from the 3-dimensional model image an analysis was made to improve the implementation method and time control
analysis using the Network Planning Critical Patch method. By using this case study of the waterway tunnel construction , an acceleration of the
provision of information is obtained to improve the implementation method and the spatial insight of the workplace to facilitate decision making.
Controlling the implementation time by utilizing information from BIM resulted in an acceleration of the implementation completion time of 2 months from
12 months to 10, with a performance efficiency level of time control to 83.3%