Technology for Shield Transferring Mined Station Tunnel

2013 
The procedure,risks and countermeasures of shield transferring mined station tunnels are studied,with a shield transferring a mined station tunnel in Guangzhou Metro as an example.A station transfer method based on track system is developed and applied in the works.In the end,the horizontal moving and upward moving of the shield are guaranteed and satisfactory results are achieved.