COMISSIONING OF THE LINEAR ACCELERATOR-INJECTOR OF TNK FACILITY

2004 
The industrial storage facility has been developed and manufactured at Budker INP SB RAS. It contains an 80 MeV electron linear accelerator-injector and two electron storage rings: the lesser 450 MeV booster ring and the main 2.5 GeV storage ring. In 2002, the work on the accelerator assembling was begun. On December, 25 of this year the accelerator was started up, and the current at the linear accelerator output was obtained. The linear accelerator schematic together with a description of the 6 meter long accelerating DAW structure which operates at 2.8 GHz, are presented in the paper. The first results of the accelerator start-up are as follows: the accelerated electron current of ~50 mA with the energy of ~55–60 MeV.